Wheatstone Liquefied Natural Gas project in Onslow, Western Australia
Wheatstone Project consists of LNG liquefaction and export plant will have an annual capacity of 15 million tonnes of LNG. In the first stage, the plant will have a gas plant, and two LNG trains with a capacity of 4.3 million tonnes per year each. Project value is A$29 billion. The Project brings together a joint venture between Chevron Australia Pty (72%) Royal Dutch Shell (6.4%) Apache Julimar Pty Ltd (13%), KUFPEC Australia (7%) and Kyushu Electric Power Co. (1.6%).
Bosnafix scope of work consists of the following:
Installation of all reinforcement on concrete structures including RC slab foundations, RC walls associated with site preparation works.
- Prefabrication & installation of 400 pile cages.
- Total reinforcement tonnage 1000T.
- Workforce will peak at 1 Supervisor and 15 steelfixers.
Project Dates: September 2013 until February 2014
Client: Thiess
EPCM: Bechtel
Owner: Chevron